Project Scope

No Project too complex

Our team played a crucial role in the successful start-up and commissioning of three GE TM2500 gas turbines, each generating 25 MW of power From the initial design review to the final handover, every phase of the project was executed with meticulous attention to detail.

Seamless Execution

The scope encompassed extensive electrical and instrumentation work, ensuring seamless integration of the turbines into the existing power infrastructure. Civil and mechanical construction supervision was carried out with a strong emphasis on structural integrity and operational efficiency